    Lots of talk keeps circulating around the thought that it can be partially open with just the old buildings for the soft opening. I would just like to point out that the first 3 floors of the tower are essentially the heart of the resort. These are where the lobby is, the bulk of the restaurants are, the night spot, and lots of the additional amenities. I understand that they could probably get by with the top floors not being complete from a room perspective, but if these main parts of the tower aren't 100%, then you don't have a functioning resort.

    I am still very optimistic as well, and I am glad there are several of us that are. Even though I have laid some pipe in my day, I don't even want to use my brain power to speculate the resort readiness at this point. I am not an architect/builder/engineer/porn-star/construction worker/contractor. So no matter what I say, I am basically talking out of my ass. Steve's perspective does make logical sense with the timeframe things have been done compared to what the time they have left. And Trish also makes some good points and that water tight (haha the word tight just doesn't seem to feel right saying on this forum) time perspective also makes sense to me.

    I just know, from watching construction in my area, that there is a huge 5 story apartment complex being built along my commute. One day it seemed like it was just starting and was at that structural framing for a while, then next thing I know, what seemed like overnight, I am looking at the building and thinking people are about to move in...and that's even with them fighting shit weather conditions this time of year.
     
    Last edited: Mar 16, 2017
  2. Cortus

    Cortus Regular Registered Member

    Joined:
    Aug 19, 2012
    Messages:
    166
    Likes Received:
    169
    Location:
    Cypress, Tx
    Ratings:
    +181 / 0
    We couldn't get a room for Halloween, so we are going end of Sept. I am sure we will have a blast no matter if there is still construction going on or not.
     
  3. Mark and Staci

    Mark and Staci I can choose my own title Registered Member

    Joined:
    Oct 7, 2012
    Messages:
    1,204
    Likes Received:
    1,550
    Location:
    Tejas
    Ratings:
    +1,892 / 4
    We are booked for Halloween. All we really need is a bed, shower, buffet, and a pool bar. Other than that, they can continue working all they want!
     
    • Like Like x 3
    • Agree Agree x 3
    • List
  4. TomAndTabi

    TomAndTabi June Junkies 4ever Registered Member

    Joined:
    Oct 15, 2010
    Messages:
    1,252
    Likes Received:
    376
    Location:
    Fort Worth, TX
    Ratings:
    +425 / 0
    I'm banking on a few things:
    First, they are HEAVILY promoting August 15 for the re-open on Facebook and Twitter. If they don't open, they will suffer badly from the bad PR.
    Second, it's a soft open, hence the low prices. Will everything be open and functional? Highly doubtful, but as long as the Sexy Pool is open, the bars are serving, you have some places to eat and a place to crash, everything will be fine.
    Third, I've felt Steve has been open and honest with us and it's of his opinion that the resort will be open on August 15. That alone is enough for me!
     
    • Like Like x 9
    • Optimistic Optimistic x 1
    • List
  5. halifaxdan

    halifaxdan I can choose my own title Registered Member

    Joined:
    Mar 19, 2008
    Messages:
    1,682
    Likes Received:
    42
    Location:
    Halifax NS Canada
    Ratings:
    +49 / 2
    $50 american ? I'll take that bet
     
  6. halifaxdan

    halifaxdan I can choose my own title Registered Member

    Joined:
    Mar 19, 2008
    Messages:
    1,682
    Likes Received:
    42
    Location:
    Halifax NS Canada
    Ratings:
    +49 / 2
    Not trying to disagree with Steve, but from my experience in building these kind of structures, the slabs and columns is the fast part. The finishes is what takes time. I hope this time I'm wrong
     
    • Like Like x 2
    • Agree Agree x 1
    • List
  7. wakey2som

    wakey2som Guru Registered Member

    Joined:
    Jul 14, 2014
    Messages:
    791
    Likes Received:
    440
    Location:
    Wakefield UK
    Ratings:
    +496 / 0
    Everyone seems to be focusing on the new tower structure, has anyone any idea if all the rest of the rooms and areas are already being upgraded or are they just sat with nothing being done at the moment?
     
  8. Steve

    Steve Administrator Owner

    Joined:
    Feb 14, 2003
    Messages:
    17,466
    Likes Received:
    4,979
    Location:
    Cancun
    Ratings:
    +7,261 / 14
    Ok, you're on. Remember, open on August 15, not finished.
     
  9. Restling

    Restling I can choose my own title Registered Member

    Joined:
    Dec 30, 2012
    Messages:
    1,612
    Likes Received:
    818
    Ratings:
    +1,635 / 4
    It would be great to get a little scoop on that for sure.
     
  10. LadynTramp

    LadynTramp I can choose my own title Registered Member

    Joined:
    Apr 28, 2013
    Messages:
    2,542
    Likes Received:
    261
    Location:
    USA
    Ratings:
    +420 / 6

    How about a "Sustantially Complete Date" poll. $100 all in. Closest date chosen prior to announced Substantially Complete date, winner takes all? Or the same poll without the cash. Either would require photographs of significant areas.

    Sustantially Complete would include all restaurants, all tower rooms, BASH, and all public areas.
     
Thread Status:
Not open for further replies.
  1. This site uses cookies to help personalise content, tailor your experience and to keep you logged in if you register.
    By continuing to use this site, you are consenting to our use of cookies.
    Dismiss Notice